- 喷泉工程主要工艺流程
- 本站编辑:杭州海旭环境科技有限公司发布日期:2019-04-10 13:16 浏览次数:
喷泉工程主要工艺流程:
1.预制及加工主要工艺流程 A、预制管道:放样画线→切割下料→钢管变曲→主管打孔→立管套丝→泵口加工→焊接立管→焊接法兰→一次清洗→二次镀锌→ 运往施工现场。 B、喷头加工:熔铜→铸造→车床车削→抛光处理→防腐处理→ 合格入库。 C、控制设备:元件检测→线路板焊接→整板调试→组件安装→ 整机调试→老化试验→合格入库。 D、配电设备:机箱加工→电气设备安装与连线→合格出厂。
2.现场设备安装主要工艺流程 A、管路及设备安装:管路拼装→水泵固定→检漏试验→二次清洗→系统接驳→管道二次防腐处理→待系统调试。 B、灯光安装:灯具定位→灯具接线→系统检测调线 C、电缆的铺设及防水连接:泵、灯、接线按图纸规定走线→连接接线盒→泵灯按图编号→电缆沿电缆沟铺设到控制室→系统调试。 D、配电控制设备安装:控制及配电设备在控制室按图就位→按线缆编号→将负载设备接入控制设备的相应端子→电控柜接零线→ 线路、电气设备检查绝缘
3.系统调试 系统安装完成后,进行系统调试。
The main process of the fountain project:
1. Prefabrication and processing main process A, prefabricated pipelines: sample drawing line → cutting down material → steel pipe bending → supervisor perforation → riser sleeve → pump processing → welding riser → welding flange → once cleaning → secondary galvanization → shipped to the construction site. B, nozzle processing: melting copper → casting → lathe turning → polishing treatment → anti-corrosion treatment → qualified entry. C, control equipment: component detection → circuit board welding → whole board debugging → component installation → whole machine debugging → aging test → qualified entry. D, distribution equipment: chassis processing → electrical equipment installation and connection → qualified factory.
2. Field equipment installation main process A, pipeline and equipment installation: pipeline assembly → pump fixation → leak detection test → secondary cleaning → system connection → pipeline secondary corrosion treatment → system debugging. Lighting Installation: Lamp positioning → Lamp wiring → System detection tweak C, cable laying and waterproof connection: pump, lamp, wiring alignment according to the rules of the drawing → connection junction box → pump lamp number → cable laying along the cable ditch to the control room → System debugging. Distribution control equipment installation: control and distribution equipment in the control room according to the map → cable number → connecting the load equipment to the corresponding terminal of the control equipment → electrical control cabinet connection zero line → circuit, electrical equipment inspection insulation
3. After the system debugging system is installed, the system is debugged.